Skyview Road Pedestrian Bridge - Weekly Status

We are continuing with the construction of Skyview Road Pedestrian Bridge over French Valley Channel in the Community of French Valley. The bridge will cross a gap along Skyview Road where there is no existing road crossing at French Valley Channel. The bridge will provide a path between the French Valley Library, located on the northwest side of the bridge, and the Susan LaVorgna Elementary School, located at the southeast corner of the intersection of Skyview Road and Via Santiago/Algarve Avenue. It will provide multipurpose access for both pedestrians and bicyclists, with no vehicular travel other than access for emergency vehicles.


The contractor continues working on the falsework (temporary supporting structure for bridge construction).


Estimate completion: Summer 2026


No traffic impact. Will monitor and minimize construction noise to adjacent neighborhood. Thank you for your understanding.

Skyview Road Pedestrian Bridge - Weekly Status

Construction Update: Skyview Road Pedestrian Bridge

Construction continues on the Skyview Road Pedestrian Bridge over the French Valley Channel in the Community of French Valley. This new bridge will span the existing gap along Skyview Road, creating a connection between the French Valley Library (on the northwest side) and Susan LaVorgna Elementary School (at the southeast corner of Skyview Road and Via Santiago/Algarve Avenue).

The bridge is designed to provide safe, multipurpose access for pedestrians and bicyclists, while allowing emergency vehicle access only—no regular vehicle traffic.

Crews are currently working on the falsework (temporary support structure) for the bridge.

Estimated completion: Summer 2026

There are no traffic impacts at this time. Construction noise will be monitored and minimized to reduce impact on nearby neighborhoods. Thank you for your patience and understanding as we improve connectivity in your community.

Skyview Road Pedestrian Bridge - Weekly Status

We are continuing with the construction of Skyview Road Pedestrian Bridge over French Valley Channel in the Community of French Valley. The bridge will cross a gap along Skyview Road where there is no existing road crossing at French Valley Channel. The bridge will provide a path between the French Valley Library, located on the northwest side of the bridge, and the Susan LaVorgna Elementary School, located at the southeast corner of the intersection of Skyview Road and Via Santiago/Algarve Avenue. It will provide multipurpose access for both pedestrians and bicyclists, with no vehicular travel other than access for emergency vehicles.


Crews continue working on the falsework (temporary supporting structure for bridge construction).


Estimated completion: Summer 2026


No traffic impact. Will monitor and minimize construction noise to adjacent neighborhood. Thank you for your understanding.

Skyview Road Pedestrian Bridge Weekly Status

We are continuing with the construction of Skyview Road Pedestrian Bridge over French Valley Channel in the Community of French Valley. The bridge will cross a gap along Skyview Road where there is no existing road crossing at French Valley Channel. The bridge will provide a path between the French Valley Library, located on the northwest side of the bridge, and the Susan LaVorgna Elementary School, located at the southeast corner of the intersection of Skyview Road and Via Santiago/Algarve Avenue. It will provide multipurpose access for both pedestrians and bicyclists, with no vehicular travel other than access for emergency vehicles.

The contractor is working on the falsework (temporary supporting structure for bridge construction).

Estimate completion: Summer 2026

No traffic impact. Will monitor and minimize construction noise to adjacent neighborhood. Thank you for your understanding.

Skyview Road Pedestrian Bridge - Weekly Status

We are continuing with the construction of Skyview Road Pedestrian Bridge over French Valley Channel in the Community of French Valley. The bridge will cross a gap along Skyview Road where there is no existing road crossing at French Valley Channel. The bridge will provide a path between the French Valley Library, located on the northwest side of the bridge, and the Susan LaVorgna Elementary School, located at the southeast corner of the intersection of Skyview Road and Via Santiago/Algarve Avenue. It will provide multipurpose access for both pedestrians and bicyclists, with no vehicular travel other than access for emergency vehicles.

The contractor is working on the falsework (temporary supporting structure for bridge construction).

Estimated completion: Summer 2026

No traffic impact. We will monitor and minimize construction noise to adjacent neighborhood. Thank you for your understanding.

Skyview Road Pedestrian Bridge - Weekly Status

We are continuing with the construction of Skyview Road Pedestrian Bridge over French Valley Channel in the Community of French Valley. The bridge will cross a gap along Skyview Road where there is no existing road crossing at French Valley Channel. The bridge will provide a path between the French Valley Library, located on the northwest side of the bridge, and the Susan LaVorgna Elementary School, located at the southeast corner of the intersection of Skyview Road and Via Santiago/Algarve Avenue. It will provide multipurpose access for both pedestrians and bicyclists, with no vehicular travel other than access for emergency vehicles.


The contractor completed the bridge substructure (supporting reinforced concrete columns). We have begun to erect falsework (temporary supporting structure for bridge construction).


Estimated completion: Summer 2026


No traffic impact. Will monitor and minimize construction noise to adjacent neighborhood. Thank you for your understanding.

Skyview Road Pedestrian Bridge - Weekly Status

We are continuing with the construction of Skyview Road Pedestrian Bridge over French Valley Channel in the Community of French Valley. The bridge will cross a gap along Skyview Road where there is no existing road crossing at French Valley Channel. The bridge will provide a path between the French Valley Library, located on the northwest side of the bridge, and the Susan LaVorgna Elementary School, located at the southeast corner of the intersection of Skyview Road and Via Santiago/Algarve Avenue. It will provide multipurpose access for both pedestrians and bicyclists, with no vehicular travel other than access for emergency vehicles.

The contractor completed the bridge substructure (supporting reinforced concrete columns). We have also begun to erect falsework (temporary supporting structure for bridge construction).

Estimated completion: Summer 2026

No traffic impact. We will monitor and minimize construction noise to adjacent neighborhood. Thank you for your understanding.

Skyview Road Pedestrian Bridge - Weekly Status

We are continuing with the construction of Skyview Road Pedestrian Bridge over French Valley Channel in the Community of French Valley. The bridge will cross a gap along Skyview Road where there is no existing road crossing at French Valley Channel. The bridge will provide a path between the French Valley Library, located on the northwest side of the bridge, and the Susan LaVorgna Elementary School, located at the southeast corner of the intersection of Skyview Road and Via Santiago/Algarve Avenue. It will provide multipurpose access for both pedestrians and bicyclists, with no vehicular travel other than access for emergency vehicles.

The contractor is working on the bridge substructure (supporting reinforced concrete columns) and preparing to erect falsework (temporary supporting structure for bridge construction).



Estimate completion: Summer 2026

No traffic impact. Will monitor and minimize construction noise to adjacent neighborhood. Thank you for your understanding.



Skyview Pedestrian Bridge - Weekly Status

We are continuing with the construction of Skyview Road Pedestrian Bridge over French Valley Channel in the Community of French Valley. The bridge will cross a gap along Skyview Road where there is no existing road crossing at French Valley Channel. The bridge will provide a path between the French Valley Library, located on the northwest side of the bridge, and the Susan LaVorgna Elementary School, located at the southeast corner of the intersection of Skyview Road and Via Santiago/Algarve Avenue. It will provide multipurpose access for both pedestrians and bicyclists, with no vehicular travel other than access for emergency vehicles.

The contractor is working on the bridge substructure (supporting reinforced concrete columns).



Estimate completion: Summer 2026

No traffic impact. Will monitor and minimize construction noise to adjacent neighborhood. Thank you for your understanding.



Skyview Road Pedestrian Bridge - Weekly Status

Skyview Road Pedestrian Bridge - Weekly Status

We are continuing with the construction of Skyview Road Pedestrian Bridge over French Valley Channel in the Community of French Valley. The bridge will cross a gap along Skyview Road where there is no existing road crossing at French Valley Channel. The bridge will provide a path between the French Valley Library, located on the northwest side of the bridge, and the Susan LaVorgna Elementary School, located at the southeast corner of the intersection of Skyview Road and Via Santiago/Algarve Avenue. It will provide multipurpose access for both pedestrians and bicyclists, with no vehicular travel other than access for emergency vehicles.

The contractor currently working on the bridge substructure (supporting reinforced concrete columns).

Estimate completion: Summer 2026

No traffic impact. Will monitor and minimize construction noise to adjacent neighborhood. Thank you for your understanding.

Skyview Road Pedestrian Bridge - Weekly Status

We are continuing with the construction of Skyview Road Pedestrian Bridge over French Valley Channel in the Community of French Valley. The bridge will cross a gap along Skyview Road where there is no existing road crossing at French Valley Channel. The bridge will provide a path between the French Valley Library, located on the northwest side of the bridge, and the Susan LaVorgna Elementary School, located at the southeast corner of the intersection of Skyview Road and Via Santiago/Algarve Avenue. It will provide multipurpose access for both pedestrians and bicyclists, with no vehicular travel other than access for emergency vehicles.

The contractor currently working on drainage systems and preparing to start the bridge construction.



Estimate completion: Summer 2026

No traffic impact. We will monitor and minimize construction noise to adjacent neighborhood. Thank you for your understanding.



Skyview Road Pedestrian Bridge - Weekly Update

Skyview Road Pedestrian Bridge Construction Update

Community of French Valley

Construction is ongoing for the Skyview Road Pedestrian Bridge over the French Valley Channel. This bridge will span the existing gap along Skyview Road where there is currently no crossing, connecting the French Valley Library on the northwest side to Susan LaVorgna Elementary School at the southeast corner of Skyview Road and Via Santiago/Algarve Avenue. The bridge will provide a multipurpose path for pedestrians and bicyclists, with vehicular access limited to emergency vehicles only.

At this time, the contractor is working on drainage system installation and preparing the site for bridge construction.

Estimated Completion: Summer 2026

Traffic Impact: None.

Additional Notes: Construction noise will be monitored and minimized to reduce impacts on the surrounding neighborhood.

Thank you for your patience and understanding.

Skyview Road Pedestrian Bridge - Weekly Status

We are continuing with the construction of Skyview Road Pedestrian Bridge over French Valley Channel in the Community of French Valley. The bridge will cross a gap along Skyview Road where there is no existing road crossing at French Valley Channel. The bridge will provide a path between the French Valley Library, located on the northwest side of the bridge, and the Susan LaVorgna Elementary School, located at the southeast corner of the intersection of Skyview Road and Via Santiago/Algarve Avenue. It will provide multipurpose access for both pedestrians and bicyclists, with no vehicular travel other than access for emergency vehicles. Crews are currently working on drainage systems and preparing work area for bridge construction.



Estimate completion: Summer 2026

No traffic impact. Will monitor and minimize construction noise to adjacent neighborhood. Thank you for your understanding.



Skyview Road Pedestrian Bridge - Weekly Status

We are continuing with the construction of Skyview Road Pedestrian Bridge over French Valley Channel in the Community of French Valley. The bridge will cross a gap along Skyview Road where there is no existing road crossing at French Valley Channel. The bridge will provide a path between the French Valley Library, located on the northwest side of the bridge, and the Susan LaVorgna Elementary School, located at the southeast corner of the intersection of Skyview Road and Via Santiago/Algarve Avenue. It will provide multipurpose access for both pedestrians and bicyclists, with no vehicular travel other than access for emergency vehicles. Crews are currently working on drainage systems and preparing work area for bridge construction.



Estimate completion: Summer 2026

No traffic impact. We will monitor and minimize construction noise to adjacent neighborhood. Thank you for your understanding.



Skyview Bridge Pedestrian Bridge - Weekly Status

We are continuing with the construction of Skyview Road Pedestrian Bridge over French Valley Channel in the Community of French Valley. The bridge will cross a gap along Skyview Road where there is no existing road crossing at French Valley Channel. The bridge will provide a path between the French Valley Library, located on the northwest side of the bridge, and the Susan LaVorgna Elementary School, located at the southeast corner of the intersection of Skyview Road and Via Santiago/Algarve Avenue. It will provide multipurpose access for both pedestrians and bicyclists, with no vehicular travel other than access for emergency vehicles. Crews are currently working on drainage systems and setting up field offices.



Estimate completion: Summer 2026

No traffic impact. Will monitor and minimize construction noise to adjacent neighborhood. Thank you for your understanding.